Expansion of the School EB1 of Oliveira do Arda

Expansion of the School EB1 of Oliveira do Arda

Expansion of the School EB1 of Oliveira do Arda

CHALLENGE

Preservation of the façade, taking into account the total demolition of the interior.

 

SOLUTION

The walls of the main façade had to be maintained and, as such, a temporary metal structure was executed to contain these walls. The reason for the partial demolition of the buildings was related to the state of the buildings and to regulatory reasons.

In order to contain the walls of the main facade, a metal support structure in SHORFLEX HD® and SHORFLEX LT ® was used.

Metalusa’s Engineering department supervised the work, always ensuring the correct use of the equipment.

Related products

SHORFLEX HD
CONTAINMENT SYSTEM

logo compete 2020
Cookie Settings

Metalusa may use cookies to remember your login data, collect statistics to optimize the functionality of the site and to perform marketing actions based on your interests.

These cookies are necessary to allow the main functionality of the website and are automatically activated when you use this website.
These cookies allow us to analyze the use of the website, so that we can measure and improve its performance.
They allow you to be in contact with your social network, share content, send and post comments.

Required Cookies They allow you to personalize the commercial offers that are presented to you, directing them to your interests. They can be own or third party cookies. We warn you that, even if you do not accept these cookies, you will receive commercial offers, but without meeting your preferences.

Functional Cookies They offer a more personalized and complete experience, allow you to save preferences, show you content relevant to your taste and send you the alerts you have requested.

Advertising Cookies They allow you to be in contact with your social network, share content, send and post comments.